Lightweight foam cellular screed laid to falls and cross falls (minimum 1% slope) trowel-applied smoothly finish. Mix design shall be in accordance with manufacturer recommendation.
Concrete upstands shall be dry, clean and smoothly finished; CMU (concrete Masonry Units) upstands must be properly plastered smoothly finished.
Separation Layer:
Apply a layer of non-woven geotextile separation layer with minimum of 100mm wide overlaps, loosely laid, above the prepared substrates, minimum of 50mm wide overlaps to the adjacent sheets.
Membrane Placement:
The PVC membrane shall be loose laid over the geotextile layer. The roof perimeter has to be fixed mechanically to keep the membrane in place.
Overlap seams are welded by electric hot air welding equipment, such as manual hot air welding machines and pressure rollers or automatic hot air welding machines with controlled hot air temperature.
Welding parameters including temperature, machine speed, air flow, pressure and machine settings must be evaluated, adapted
and checked on site according to the type of equipment and the climatic situation prior to welding.
The effective width of welded overlaps by hot air should be minimum of 20mm.
The seams must be mechanically tested with seam probing method to ensure the integrity / completion of the weld. Any imperfections must be rectified by hot air welding.